Embarkation Facility Installation Commences

As of the 17th July 2017, works have begun for the installation on the new embarkation facilities along the East Quay Ballast.  This will allow us to provide leisure boating facilities to the public.

Below is a photo diary of the project.  We will update this regularly until completion.

17th July 2017

Delivery of Piles

Delivery of Piles

18th July 2017

Pitching the Pile

Pitching the Pile

 

Vibro Pile driver

Vibro Pile driver

 

Impact Pile Driver

Impact Pile Driver

19th July 2017

All four piles in place

All four piles in place

 

Delivery of the Pontoons

Delivery of the Pontoons

 

Preparing for Lift

Preparing for Lift

 

Swinging the Pontoon

Swinging the Pontoon

 

Pontoon in the water

Pontoon in the water

 

Swinging second pontoon

Swinging second pontoon

 

Both Pontoons in the water

Both Pontoons in the water

Search the archive

Gallery

News

Harbour Board Meeting

Published: Thursday 10 August

If you would like to come along, the details are here.

Whitstable Harbour Pilotage Review

Published: Monday 24 July

The requirement for Pilotage into Whitstable Harbour is to be reviewed.

Events

Defending Our Shores

01 July - 01 December

Threats to Whitstable from wars, floods and smugglers Whitstable is situated on the coast of the Thames Estuary, which brings great advantages of... at Whitstable Museum and Gallery

Beverley Fisher

16 August - 22 August

After a long break from exhibiting, Beverley is back with an exhibition of black and white drawings, packed with character of some of the nation's... at Horsebridge Arts and Community Centre